July 2015 Site Progress Notes


Perimeter security fence and silt fence has been installed across Ashton Fields and temporary culvert crossings were installed in June across Longmoor, New Colliters and Old Colliters Brooks in advance of the start of major earthworks.

Construction of the busway embankment started on 6th July at Long Ashton Park and Ride with the installation of the drainage blanket and haul route to allow band drains in August this year.

In parallel with this, the ecology team have been busy clearing the vegetation from the footprint of the Flood Compensation area which is scheduled to be excavated next month.

Along the remainder of the route, ground investigation and service location has continued.