Section 3 Piling Update

On the week commencing Monday 4th April we will start piling on the Avon Crescent Ramp. This will involve a piling rig auguring 190 piles at 900mm diameter socket to a depth of approximately 17m. The auguring process is relatively quiet, with concrete delivered by standard road truck mixers and pumped into the augured hole. Concrete will be delivered via the traffic management on Cumberland road.

This operation will take up to 5 weeks.

Balfour Beatty will only install the piles during normal working hours (7.30-18hrs).